Objectors over Grantham Southern Relief Road have county 'over a barrel' says Highways chief




Lincolnshire County Council’s highways chief has said official objectors to the Grantham Relief Road have them ‘over a barrel’ when it comes to getting the new route approved.

Network Rail was among several objectors to the legal orders and land acquisitions for the £81 million project which is hoped to join the B1174 to the A1.

The relief road would look to link the A52 at Somerby Hill to the A1 which should reduce congestion in the town centre.

However, Richard Davies, LCC’s executive councillor for highways, said the authority was now ‘pretty close to having done a deal with them’.

The councillor made his comments after the county council gave an update to members about the road's progress earlier this week.

Grantham-based Coun Davies also says it was difficult to get initial approval from organisations such as Highways England.

He said: “Again, frustrating really isn’t it that Highways England and Network Rail, two Government arms, are so difficult to work with, especially when we talk to them on a weekly basis and have done about all of the projects for years and at the last minute they appear with these concerns and problems?

“It’s incredibly frustrating but I’m afraid it’s the nature of road building in the UK.”

Asked what the solution to the objections was, he replied: “Agreeing to give them the money they want, simply put.

“In one instance for Network Rail wanted some car parking space, they’d never mentioned that previously and you think why would you wait till now to do that?

“You basically have to agree with what they’re asking for — these things are called ransoms for a reason and the fact is they have us over a barrel. The alternative is we don’t build the road.”

He said however, that the project would only be delayed by a few months since the county council had ‘managed to deal with it and expedite concerns quickly’.

A Network Rail spokesperson said: “We continue to work closely with Lincolnshire County Council on the construction of the Grantham Southern Relief Road.”

A Highways England spokesperson said however: “We’re supportive of measures to improve journeys around Grantham and have raised no objections to the council’s plans. We look forward to continuing to work closely with the local authority as the project moves forward.”

Coucillor Davies is concerned that a public enquiry could be held at the end of the year if a solution isn’t found.

If objections are withdrawn the enquiry will not go ahead.

Objections to the legal orders originally included:

Network Rail – affected land, width size of the easement, details of CPO, access rights to new access track and potential additional easements

Zurich – justification and use of compulsory purchase order

Western Power Distribution – protection of interests in vicinity of the scheme

Grantham Motor Company – site access, position of transporter layby and stopping up proposal



COMMENTS
()


Iliffe Media does not moderate comments. Please click here for our house rules.

People who post abusive comments about other users or those featured in articles will be banned.

Thank you. Your comment has been received and will appear on the site shortly.

 

Terms of Comments

We do not actively moderate, monitor or edit contributions to the reader comments but we may intervene and take such action as we think necessary, please click here for our house rules.

If you have any concerns over the contents on our site, please either register those concerns using the report abuse button, contact us here.

This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies - Learn More